Photos of our remodeling to support laser experiments.
You might also want to visit our general photo gallery.


 
PULSAR, September 2012 PULSAR, July 2012 Laser Assembly, July 2012
Ready for Science
Sept 2012
PULSAR
July 2012
Laser Assembly
July 2012

 
Laser Arrives, July 2012 East Floor, July 2012 West Floor, June 2012
Laser Arrives
July 2012
East Floor
July 2012
West Floor
June 2012

 
More Cables and Trays, June 2012 Cables and Trays, May 2012 Finishing, May 2012
More Cables
June 2012
Cables & Trays
May 2012
Walkthrough
May 2012

 
Almost there..., May 2012 Almost there..., May 2012 Finishing, May 2012
Wall Down, Trays Up
May 2012
Amost There...
May 2012
Finishing
May 2012

 
Ceilings, May 2012 Electrical Work, May 2012 Ductwork, May 2012
Ceilings
May 2012
Electrical
May 2012
Ductwork
May 2012

 
Rapid Progress, May 2012 Suspended Ceiling Hangars, May 2012 Closing In, May 2012
Rapid Progress
May 2012
Ceiling Hangars
May 2012
Closing In
May 2012

 
Electrical Work Begins, April 2012 More Walls Rise, April 2012 Roof Beams, April 2012
Electrical Work
Apr 2012
More Walls
Apr 2012
Roof Beams
Apr 2012

 
Construction Continues, April 2012 Walls Rise, April 2012 Prefab Arrives, April 2012
Construction Continues
Apr 2012
Walls Rise
Apr 2012
Prefab Arrives
Apr 2012

 
HVAC Equipment, April 2012 PULSAR Floor, March 2012 HITS HVAC, March 2012
HVAC Equipment
Apr 2012
PULSAR Floor
Mar 2012
HITS HVAC
Mar 2012

 
Trenches Covered with Concrete, February 2012 Ductwork, February 2012 Temporary Walls, February 2012
Trenches Paved Over
Feb 2012
Ductwork
Feb 2012
Temporary Walls
Feb 2012

 
AC Plumbing, January 2012 Trenching, January 2012 HITS, January 2012
AC Plumbing
Jan 2012
Trenching
Jan 2012
HITS
Jan 2012

 
New Stairs, December 2011 Networking, Optical Tables and More, December 2011 MOTRIMS, November 2011
New Stairs
Dec 2011
Network & Optical Tables
Dec 2011
MOTRIMS
Nov 2011

 
HITS Area, November 2011 MOT Area, October 2011 HITS Construction, October 2011
HITS Area
Nov 2011
Reassembling MOT
Oct 2011
HITS Construction
Oct 2011

 
New Construction in Former MOT Area MOT Area Demolition, September 2011 Lab Demolition, September 2011
Construction for HITS
Oct 2011
More MOT Demolition
Sep 2011
More Lab Demolition
Sep 2011

 
Moving the MOT MOT Area Demolition, September 2011 Lab Demolition, September 2011
Moving the MOT
Sep 2011
MOT Demolition
Sep 2011
Lab Demolition
Sep 2011

 